MTO, BOM and BOQ


Piping design tips & guide  for more follow me on Facebook 

The question:

What is the meaning of MTO, BOM and BOQ and how do I start this ..... I mean some useful tips to make a BOM, MTO, BOQ...like what are the things to be considered, what all are mandatory... etc. ?”


My answer: (Based on my experience)Piping design tips & guide

MTO means Material Take-Off. This is the action of counting of the pieces and parts needed to fabricate, purchase and or construct something. (“Have you started the MTO yet? - Have you completed the MTO yet?”)

BOM means Bill of Material. This is normally a listing of only the material shown on an individual specific drawing such as a piping Isometric. (“Have you checked all the BOM’s for the Area 10 Isometrics?)

BOQ means Bill of Quantity (also called Material Summary). This is the totaling of all the quantities from all the BOM’s from all the project to send to a piping supplier for pricing or purchase.

There are normally three material take-offs sessions during a process plant project. These are preliminary, secondary and final.
Preliminary MTO:
What is it? – A preliminary MTO is a material take-off very early in the design process when only a limited amount of information is known and very little detail has been developed.

Why is it done? - A preliminary MTO is normally done for two reasons. The first is to assist with the early "order-of-magnitude" (+/- 10%) estimate for the overall project. The second reason is to issue early order of magnitude "RFQ's" (Request for Quote) for piping materials

When is it done? - The preliminary MTO is only possible when there is a Plot Plan that is "Approved" by the Client or has been issued to the client for approval. This is done long before there is any detailed work started on the 3D design model.
Who does it? - A preliminary MTO is best done by very strong well experienced senior piping designers who are familiar with the project.


How is it done? - For the preliminary MTO we used a formatted form on which we could indicate the number or amount of material required for each line. On the form I would identify the line number along with the line class. I would then look at this line on the P&ID and on the Plot Plan and determine the routing of the pipe. Then in the boxes (on the form) I would then mark the amount of pipe required for each size required for that line. Then I would count the number of fittings required, starting with 90 degree elbows. Then continuing through all the other inline fittings and online fittings. After the fittings I would count all the flanges by size. Then I would count all the

 valves from the P&ID. The high point vents and low point drains would be made last based on an educated guess. Then I would take another form and do another line. As I did each line I would "Yellow" off the line on the P&ID so at the end all the lines are accounted for. As the forms were completed they would be reviewed by the Area Supervisor and then forwarded to the Material Control Group who would process the data to produce the RFQ's

Secondary MTO:
Why is it done? - The primary reason for the Secondary MTO is to update quantities for the issue of the actual Purchase orders for piping material. A second reason is to update the project estimate.


When is it done? - The Secondary MTO can only be done when there is significant progress completed on the 3D design model (or other electronic design method). However it must be done early enough to insure that the procurement (purchase and delivery) of the piping material to the field will fit the overall project schedule.

Who does it? - The Material Control Group.
How is it done? - The Material Control Group would access the electronic data base and down-load all the material available at that time. Some factoring would be done by the Material Control Group and the Piping Design Leads to allow for work not done yet.

Final MTO –
Why is it done? - The final MTO is done first to identify any item added late in the project or anything that was missed on the Preliminary or Secondary MTO's. The second reason for the Final MTO is to get a fix on the final job costs.


When is it done? - The Final MTO is done when the last Isometric has been issued.
Who does it? - The Material Control Group.

How is it done? - The Material Control Group would access the electronic data base and down-load all the material. Any differences between the Final MTO and the Secondary MTO would be identified. Purchase orders would be issued for the updated quantities.

Please remember this is only how it was done where I was. Use it as a guide but please do not be misled that this is the only way an MTO can be done.t

Process Flow Diagram Symbols - Equipments

Process Flow Diagram Symbols - Equipments


 is a mechanical device that takes in a medium and compresses it to a smaller volume. A mechanical or electrical drive is typically connected to a pump that is used to compress the medium.
Pumps is a mechanical device using suction or pressure to raise or move liquids, compress gases, or force air into inflatable objects such as tires. The symbols for pumps may closely resemble those for compressors.
Mixing is a device  that combine or put together to form one substance or mass.
Mixing vessel is a container that is used to blend several components together.










Heat exchanger is a device used to transfer heat energy between two process flows. Heat exchangers transfer heat energy through conductive and convective heat transfer.
Cooling towers transfer heat energy to the outside air through the principle of evaporation.
Cooler is a device, container or room that cools air through the evaporation of water or keeps cool.
Furnace is a device for heating a continuous current of air by means of a fire contained within the apparatus and without mingling the fresh air with the products of combustion.
Boiler is a closed vessel in which water or other fluid is heated.
Tank is used to store process fluids of various types, under different process conditions.Piping design tips & guide         Piping design tips & guide

Process Flow Diagram Symbols - Instruments

Process Flow Diagram Symbols - Instruments

Process Flow Diagram Symbols - Instruments





Process Flow Diagram use symbols and circles to represent each instrument and how they are inter-connected in the process.



Process Flow Diagram Symbols - Piping Lines

Process Flow Diagram Symbols - Piping Lines

Process Flow Diagram Symbols - Piping Lines


Process flow diagrams use special piping lines to represent how signals are transmitted between equipments. These symbols are used to identify how the instruments in the process connect to each other. And what type of signal is being used. (electrical, pneumatic, data, etc)

All lines to be fine in relation to process piping lines.

Major pipeline is used to connect the equipment in any position.
Major Straight line is sued to connect the equipment in the same horizontal or Vertical position.
Process connection help create the process flow between equipments. Double click process connection to edit description.

Process Flow Diagram Symbols - Valves

Process Flow Diagram Symbols - Valves

     Process Flow Diagram Symbols - Valves

Process Flow Diagram Symbols - Valves


Gate valve is a device used to control the flow of liquids and gases.
Check valve, also known as one-way valve, is to prevent the line of medium back.
Globe valve is a mechanism used to control or stop the flow of liquid or gas through a pipe.
Ball valve is a valve with a spherical disc, the part of the valve which controls the flow through it.
Butterfly valve is installed between two flanges using a separate set of bolts for each flange.
Angle valve is oriented at an angle 90 deg of gate valve.